Thursday, June 9, 2011

Deck Install Continues/ Wood Floor Install Begins

Install of Exterior Decks

Front Entry & Stair Tower

Master Bedroom Deck

Street Elevation

Master Bedroom


View from Stair- Front Entry and Second Floor Sitting/Viewing Area

Second Floor-Exterior Decking and Interior Wood Flooring

Second Floor- Main Living Space-Install of Flooring

Metal Soffit

View from Deck


View From Deck

Fireplace & Built-in Bookcase and Bench

Second Floor-Stair Tower

Second Floor-Stair Tower

Second Floor-View from Living room onto Decks and Nantucket Sound

Monday, June 6, 2011

Exterior: Decks Begin/ Interior: Drywall

Street View-First and Second Floor Decking Install Begins

Decks



Basement Stair

Basement- HRV Room



Bedroom-Drywall

Bedroom-Drywall

Bedroom-Drywall

Second Floor-Fireplace/Built in

View from Dining Room into Living Room-Drywall

Living room & Kitchen

Stair Tower/Living room

Thursday, May 26, 2011

Drywall and Exterior Finishes

 Living Room
 Living room- View of Nantucket Sound beyond
 Basement
 Exterior Finishes-Shingels & Clapboard
 Street Elevation-Front Door
 Street Elevation

Friday, May 13, 2011

Blower Door Test

Initial blower door test...

Infiltration rate BEFORE insulation = approximately 3 ACH (air changes per hour)

Insulation Begins-Closed Cell Spray Foam

Closed cell sprayed in foam in roof - r: 38

Closed cell sprayed in foam

Air sealing around the columns

Install of Mechanical Systems

HRV (heat recovery ventilator) which will provide constant fresh air (pre-warmed by exhaust air)

Exterior component of the Mini Split Heat Pump

Interior component of the Mini Split Heat Pump.  These are ultra-efficient electrical heating and cooling systems.

Exterior Work